Cost planning guide

Commercial Fit-Out Cost in New Zealand

A useful fit-out budget is not a single square-metre rate. It is a transparent model of the actual tenancy, scope, programme and risk. This guide shows what to define before comparing prices.

By AMING INTERIORS · Updated · 7 minute guide

The short answer

A commercial fit-out budget should separate design and approvals, site preparation, building services, interiors, equipment and handover. Compare quotations against the same drawings, inclusions, exclusions and GST basis. Existing conditions, access and procurement can change the total, so an allowance based only on floor area needs a site-specific scope before it can become a reliable quote.

01

Start with scope, not a headline rate

Benchmark rates can help with an early sense-check, but they rarely compare like with like.

Existing condition

Record what remains, what is removed and what can be reused. A fitted tenancy, a stripped shell and an occupied refurbishment carry different demolition, protection, services and compliance work.

Operational requirements

Translate the business into areas, customer flow, staff needs, storage, equipment, lighting, acoustics, security and cleaning requirements. These decisions shape both construction and specialist packages.

Quality and finish

Define the expected durability and presentation level for floors, walls, ceilings, joinery, fittings and signage. Without a clear finish schedule, quotations may price different outcomes.

What the rate includes

Ask whether any benchmark includes design fees, consultants, consent fees, services, furniture, IT, equipment, signage, landlord works, after-hours work, contingency and tax. Record exclusions rather than assuming them.

02

Allow for the site and approvals

Building services

Electrical capacity, data, lighting, HVAC, plumbing, drainage, fire systems and kitchen equipment interfaces can be major cost drivers. Verify existing capacity and connection points before design is fixed.

Consent and compliance

Some existing non-residential interior alterations may be exempt, but work affecting structure, specified systems, fire separations or sanitary plumbing falls outside that exemption. A first fit-out of a new shell is also outside it.

Official source: MBIE: interior alterations to existing non-residential buildings

Landlord and centre rules

Include landlord review, inductions, temporary protection, delivery routes, loading limits, shutdown approvals and required after-hours work. These constraints can affect preliminaries and productivity.

Unknown conditions

Use surveys, service investigations and targeted opening-up where appropriate. For refurbishment work, asbestos duties must be addressed before material that may contain asbestos is disturbed.

Official source: WorkSafe: managing asbestos in your building or workplace

03

Build a comparable project budget

Use one scope schedule

Issue the same coordinated information to each pricing party. Separate fixed items, provisional sums, client-supplied items and exclusions so differences are visible.

Keep contingency explicit

Set contingency according to design completeness and site uncertainty. Hold it as a managed project allowance, not as an invisible amount spread through unrelated trades.

Track decisions and changes

Record each change, its cost, programme effect and approval before work proceeds where practicable. A decision register protects the working budget from gradual scope drift.

Protect the opening date

Budget decisions should be tested against procurement and approvals. A cheaper late substitution can cost more if it delays manufacture, inspection or opening.

Quote checklist

A checklist for comparing fit-out quotations

Use these headings when requesting or reviewing a written quote. Record the amount, responsibility and exclusions for each package; this checklist does not provide market rates or a project estimate.

Compare the same scope, responsibilities and exclusions in each quotation.
Budget packageConfirm what is includedRecord separately
Design and approvalsDrawings, consultant scope and application supportAuthority fees, landlord review and client-appointed consultants
Site preparationStrip-out, disposal, protection and preparationUnknown conditions and work confirmed after opening up
Building servicesElectrical, lighting, data, plumbing, ventilation and fire-system interfacesCapacity upgrades, specialist design and landlord works
Interiors and joineryPartitions, ceilings, flooring, painting, counters and cabinetryProduct selections, provisional allowances and client-supplied materials
Equipment and signageSupply, delivery, installation and connection responsibilitiesClient purchases, freight, commissioning and access equipment
Programme and handoverSite management, access, testing, cleaning and close-out recordsAfter-hours work, travel, staged handovers and exclusions
Total and changesThe GST basis, quote validity and agreed payment stagesContingency, provisional sums and the written variation process

FAQ

Common questions

How much does a commercial fit-out cost per square metre in New Zealand?

There is no responsible universal rate. Existing condition, use, services, approvals, programme, equipment, joinery and finish level all change the scope. Use benchmark rates only as an early range, then price a site-specific brief and coordinated drawings.

Should a fit-out budget include contingency?

Yes. The amount should reflect how complete the design is and how much is known about the existing building. Keep contingency visible, controlled and linked to identified risk.

What information improves cost certainty?

A measured plan, defined use, coordinated layout, finishes, equipment, signage, services, consent assumptions, access rules, programme and a clear list of inclusions and exclusions.

Sources

Check the current requirements for the site.

This guide is practical project information, not legal, planning or compliance advice. Official requirements can change and the correct pathway depends on the building, use and proposed work.

Keep planning

Related planning guides